Fire Rated Access Panels: UK Building Regulations 2026 Guide
A fire rated access panel is part of the wall or ceiling it sits in, not an accessory. Under Approved Document B, an opening in a fire resisting wall, ceiling, compartment or protected shaft must not reduce the fire resistance of that construction. So a service access panel in a 60 minute ceiling or riser wall has to give 60 minutes too, with test evidence that matches where and how it is fitted. This guide sets out what the regulations ask for in England in 2026, what has just changed, what changes next (BS 476 classes leave Approved Document B on 2 September 2029), and how to choose and fit 1 hour fire rated access panels that pass inspection.
Quick regulations cheat sheet
| Question | Short answer |
|---|---|
| Which regulation applies? | Building Regulations 2010, Part B (fire safety). In England the guidance is Approved Document B, Volume 1 (dwellings) and Volume 2 (buildings other than dwellings), last updated 16 September 2026. |
| When does a panel need to be fire rated? | Whenever it sits in a fire resisting wall, ceiling, floor, compartment or protected shaft (riser). The panel must match the fire resistance of that element. |
| How long? | Set by the fire strategy. 30 and 60 minutes are the most common in flats, hotels, offices and schools; 2 hours is common in riser shafts and some compartment walls. |
| Which test standards? | BS EN 1634-1 for walls (fire resistance of doors and openable panels) and BS EN 1364-2 for ceilings, classified to BS EN 13501-2. BS 476 Part 20/22 results are still accepted until 2 September 2029. |
| Wall or ceiling? | They are tested separately. A panel rated 2 hours in a wall may be 1 hour in a ceiling. Check the rating for the orientation you are fitting. |
| Integrity or insulation? | Most steel access panels are rated for integrity (E). Where the fire strategy asks for insulation as well (EI), you need a panel tested for EI. |
| Higher-risk buildings | On buildings of 18m or 7 storeys and above, the panel named at Gateway 2 is the panel to buy. Swapping it later can be a controlled change. Keep the evidence for the golden thread. |
1. What Approved Document B actually requires
Approved Document B does not have a clause titled “access panels”. The requirement comes from the rules for the elements an access panel sits in. Fire resisting walls and floors that divide a building into compartments, the enclosures of protected shafts that carry services between floors, and fire resisting ceilings and cavity barriers must all keep their fire resistance where they are pierced. An access panel is an opening in that construction, so it has to give the same period of fire resistance as the wall, ceiling or shaft around it.
Approved Document B Table C1 sets the performance for fire doorsets, including doors to cupboards and service ducts, and links some of those periods to the minimum fire resistance of elements of structure in Tables B3 and B4. In practice the project fire engineer or fire strategy sets the period for each location, and the access panel schedule follows it.
Where 1 hour fire rated access panels are used
- Protected corridor and escape route ceilings where services run above a fire resisting ceiling.
- Hotel bedrooms and bathrooms, where every room has a ceiling panel over valves, fan units and pipework, repeated on every floor.
- Flats and student accommodation, at service cupboards, boxing and risers that pass through compartment floors.
- Compartment walls in offices, schools, hospitals and care homes, giving access to dampers, valves and cabling.
- Fire safety remediation, where compartmentation is being restored and every opening is surveyed, upgraded and recorded.
30 minutes, 60 minutes or 2 hours
The period comes from the element, not the panel. A 30 minute partition needs at least a 30 minute panel; a 60 minute compartment ceiling needs a 60 minute panel; a 2 hour riser wall needs a 2 hour panel. Fitting a higher rated panel than needed is acceptable. Fitting a lower one is a defect, however good the installation.
2. What has changed in 2026, and what is coming
Approved Document B was updated on 16 September 2026
The current volumes are the 2019 edition incorporating the 2020, 2022, 2025 and 2026 amendments, published on GOV.UK alongside the 2029 amendments (Approved Document B: fire safety). The 2026 amendments add guidance on second staircases and on building design to support evacuation lifts in taller residential buildings. The second staircase changes took effect in England on 30 September 2026. More stair and lift cores mean more protected shafts, and more openings that need fire rated access.
BS 476 fire resistance classes leave Approved Document B on 2 September 2029
GOV.UK confirms that the withdrawal of the national classes (the BS 476 fire tests) has been concluded, ending a long period of dual specification, and that BS EN 13501 remains in place. From 2 September 2029, references to BS 476 fire resistance classes are removed from Approved Document B. Until then a panel tested to BS 476 Part 20 or Part 22 can still be used where it suits the application. After that date, new work will look for evidence to BS EN 1634-1 classified under BS EN 13501-2. If you are specifying for a project that will run past 2029, ask for EN evidence now.
More change is on the way
The Building Safety Regulator’s consultation on further changes to Approved Document B closed on 1 July 2026 with more than 500 responses, and the government’s consultations on the Construction Products Reform White Paper and a General Safety Requirement for construction products closed in May 2026 (Grenfell Tower Inquiry: government progress report, September 2026). Both point the same way: clearer evidence for every fire safety product, and less tolerance for products that cannot show it.
3. Reading the fire test evidence
A fire rating on a product title is not evidence. Before an access panel goes on a schedule, check five things in its test report or certificate:
- The standard. BS EN 1634-1 for walls or BS EN 1364-2 for ceilings (with BS EN 1363-1 for the general test conditions), or BS 476 Part 20/22. Note which, because of the 2029 change.
- The period and the criteria. “60 minutes integrity” is an E 60 performance. EI 60 means integrity and insulation. They are not the same.
- The orientation. Wall (vertical) and ceiling (horizontal) are separate results.
- The size range. The tested or assessed maximum size. A panel larger than the evidence covers is not covered.
- The substrate. The board type, number of layers and framing used in the test. The installation has to match it.
Note also that fire integrity says nothing about smoke, air or sound. If a location also needs smoke control (BS EN 1634-3), airtightness or an acoustic rating, the panel needs those tests too.
4. Installed as tested
Most fire stopping failures at access panels come from the installation, not the product. The panel only performs as tested when it goes into the same construction it was tested in.
- Match the board. Fit into a fire rated plasterboard system of the type and thickness covered by the evidence.
- Frame the opening. Trim the opening with studs or channels as the fitting instructions show. Do not hang a panel off unsupported board.
- Cut the hole to size. An oversized hole leaves a gap the frame cannot close. Gaps must be filled with a fire stopping product suitable for the period.
- Do not modify the panel. Cutting a bead, drilling the door or adding a lock not in the evidence can void the rating.
- Record it. Photograph each panel installed, with its label or product reference, before the ceiling or wall is closed up.
5. Higher-risk buildings: Gateway 2, Gateway 3 and the golden thread
On higher-risk buildings (at least 18m or 7 storeys with at least 2 residential units, and certain hospitals and care homes), building control is the Building Safety Regulator. The fire safety products are approved as part of the Gateway 2 application, and after that a change to a fire safety measure can be a controlled or major change that needs approval before work continues. In plain terms: specify the access panel properly once, and buy that panel.
At Gateway 3 the as-built information, including what was actually fitted and where, is handed to the accountable person as part of the golden thread. For every fire rated access panel, keep:
- the product reference, size and fire rating,
- the test report or certificate reference,
- the fitting instructions used,
- its location on the drawings, and
- a photo of it installed.
6. Existing buildings and remediation
In existing residential buildings over 11m, the Fire Safety (England) Regulations 2022 require the responsible person to check communal fire doors every three months and flat entrance doors every year. Access panels in common parts are part of the same compartmentation, and fire risk assessments and remediation surveys regularly find missing, damaged or non rated panels in corridor ceilings and riser walls. When a panel is replaced, replace it like for like or better, with evidence, and record it.
7. Bulk orders: schedules, sign-off and site delivery
On a hotel, student or residential block, 1 hour fire rated access panels are ordered by the dozen or by the hundred, usually in 300, 450, 550 and 600mm sizes. Three things make that easier:
- One evidence pack per product. Each of our fire rated product pages lists the test standard, period, orientation and size limits, with datasheets and fitting instructions in technical resources.
- Quotes for sign-off. Download a quote PDF or copy a quote link from the basket, so a buyer or QS can approve the order before it is placed.
- Bulk pricing in the basket. Discounts apply automatically on orders over £250, £500 and £1,000, and stock sizes are despatched for next working day delivery when ordered before the 2.30pm cut off, with the delivery date shown before you pay.
Product highlight: our 1 hour fire rated access panels
| Panel | Fire rating | Test evidence |
|---|---|---|
| 1hr fire rated access panel, metal door, picture frame (PF/FR60/120) | 1 hour integrity in a ceiling, 2 hours in a wall | BS EN 1634-1 and BS EN 1363-1 |
| 1hr fire rated access panel, metal door, beaded frame (BF/FR60/120) | 1 hour integrity in a ceiling, 2 hours in a wall | BS EN 1634-1 and BS EN 1363-1 |
| 1hr fire rated plasterboard access panel, beaded frame (BF/FR60/120) | 1 hour integrity in a ceiling, 2 hours in a wall | BS EN 1634-1 and BS EN 1363-1 |
| 1hr fire rated ceiling access panel, metal door, picture frame | 1 hour integrity in a ceiling | BS EN 1634-1 and BS EN 1363-1 |
| FlipFix 1hr metal door, picture frame (FF/FR60) | 1 hour integrity in a wall and a ceiling up to 600 x 600mm, with the fire on the side the door opens towards | Wall to BS EN 1634-1:2014+A1:2018, ceiling to BS EN 1364-2:2018 (Warringtonfire assessment WF380206 Revision B) |
| FlipFix 1hr plasterboard door, beaded frame (FF/FR60) | 1 hour integrity in a wall and a ceiling up to 600 x 600mm, with the fire on the side the door opens towards | Wall to BS EN 1634-1:2014+A1:2018, ceiling to BS EN 1364-2:2018 (Warringtonfire assessment WF380206 Revision B) |
| 1hr fire rated, airtight, smoke tested, 30dB acoustic panel (SF-FR60) | 1 hour integrity up to 1200 x 600mm, wall and ceiling; smoke tested to 25Pa | Wall to BS EN 1634-1, ceiling to BS EN 1364-2, smoke to BS EN 1634-3, air Class 2 to BS EN 1026 |
For a whole project in one basket, the 1hr fire rated access panel multipacks come in packs of 5, 10 and 15. For risers that need 2 hours from both sides, smoke control or EI performance, see our riser doors.
Summary: fire rated access panel regulations at a glance
- Approved Document B requires openings in fire resisting construction to keep its fire resistance. An access panel in a 60 minute element needs 60 minutes.
- Check the standard, period, E or EI, orientation, size and substrate in the evidence.
- BS 476 classes leave Approved Document B on 2 September 2029. Ask for BS EN 1634-1 evidence on long projects.
- Install as tested and record every panel, especially on higher-risk buildings.
- Smoke, air and sound need their own tests.
Fire rated access panels: frequently asked questions
Do access panels need to be fire rated?
Only when they sit in fire resisting construction: a fire resisting wall, ceiling, floor, compartment or protected shaft. Then the panel must give at least the same fire resistance as that construction. A panel in an ordinary partition does not need a fire rating.
What fire rating does an access panel need?
The same period as the wall, ceiling or shaft it is fitted in, as set by the fire strategy. In flats, hotels, schools and offices that is usually 30 or 60 minutes. Riser shafts are often 2 hours.
Is BS 476 still valid for fire rated access panels?
Yes, until 2 September 2029, when references to BS 476 fire resistance classes are removed from Approved Document B. After that, evidence to BS EN 1634-1 classified to BS EN 13501-2 is expected for new work.
What is the difference between E and EI on an access panel?
E is integrity: the panel stops flames and hot gases passing through. EI adds insulation: it also limits the temperature rise on the side away from the fire. Most steel access panels are rated E. Use an EI rated product where the fire strategy asks for insulation.
Is a wall fire rating the same as a ceiling fire rating?
No. Panels are tested in each orientation separately and often achieve different periods. Our PF/FR60/120 panel, for example, is 2 hours in a wall and 1 hour in a ceiling.
Can I fit a fire rated access panel into any plasterboard?
No. Fit it into a fire rated board system matching the construction in its test evidence, framed and fixed as the fitting instructions show.
What should I keep for the golden thread?
Product reference, size, fire rating, test or certificate reference, fitting instructions, location and an installed photo for every panel.
Can I buy fire rated access panels in bulk?
Yes. Bulk discounts apply automatically in the basket on orders over £250, £500 and £1,000, multipacks are available, and you can download a quote PDF for sign-off before ordering.
Conclusion: the panel is part of the fire strategy
A fire rated access panel is a small part of a building, but it sits in the line that holds a fire back. Match the rating to the element, check the evidence, install it as tested and record it. Browse our fire rated access panels, read the loft hatch, roof hatch and dry riser cabinet regulation guides, or request a quote for a project schedule.
This guide summarises the guidance for England as at October 2026 and is not a substitute for the project fire strategy or advice from a fire engineer or building control body. Wales, Scotland and Northern Ireland have their own regulations.